Hi Experts,
My Holiday calendar Validity is from 012013 to 122013, but when i try to generate the work schedule it is only generating till 112013 Error- In Holiday CAlendar for 012014.
While Running PT60 aslo system throwsa n error that date 20120102 is beyong Holiday calendar Validity- Error while accessing public holiday calendar. i had never faced this knid of issue before. so confused a bit.
Now i have changed the date of the Holiday calendar from 2012 to 2013 but the actual calendar validity is from & to 2013. as the floting Holidays are not same in 2012.
Now when i run PT60 it is working fine.But is it a Good Practice & what is the correct solution for this????
Thanks.