Hi,

 

I need to implement a  four teams, three shifts, four weeks pattern in positive time management.

There are 40 workmen divided into 4 teams of 10 workmen each. Team1, Team2, Team3 and Team4.

Issues is that all the four teams (total 40 workmen) belong to same PSA (Production floor) and same ESG(Workmen).

 

1. Can this be achieved by one work schedule rule? If yes please suggest how to do that.

2. If more than one work schedule rule is required, how to set the work schedule in the IT0007 (because the SCHKZ defaults on the PSA and ESG)?

 

Thanks, Rose,

 

Detailed scenario described:

 

DWS10600-1400
DWS21400-2200
DWS32200-0600
Team1
DWS1DWS1DWS1DWS1DWS1DWS1DWS1Week1
DWS2DWS2DWS2DWS2DWS2DWS2DWS2Week2
DWS3DWS3DWS3DWS3DWS3DWS3DWS3Week3
OFFOFFOFFOFFOFFOFFOFFWeek4
Team2
DWS2DWS2DWS2DWS2DWS2DWS2DWS2Week1
DWS3DWS3DWS3DWS3DWS3DWS3DWS3Week2
OFFOFFOFFOFFOFFOFFOFFWeek3
DWS1DWS1DWS1DWS1DWS1DWS1DWS1Week4
Team3
DWS3DWS3DWS3DWS3DWS3DWS3DWS3Week1
OFFOFFOFFOFFOFFOFFOFFWeek2
DWS1DWS1DWS1DWS1DWS1DWS1DWS1Week3
DWS2DWS2DWS2DWS2DWS2DWS2DWS2Week4
Team4
OFFOFFOFFOFFOFFOFFOFFWeek1
DWS1DWS1DWS1DWS1DWS1DWS1DWS1Week2
DWS2DWS2DWS2DWS2DWS2DWS2DWS2Week3
DWS3DWS3DWS3DWS3DWS3DWS3DWS3Week4

 

 

Thanks, Rose.