Quantcast
Channel: SCN : Discussion List - SAP ERP Human Capital Management (SAP ERP HCM)
Viewing all articles
Browse latest Browse all 7926

Delimit Rounding & Counding Rule

$
0
0

Dear Experts,

 

Please suggest how to delimit Rounding & counting rule for below requirement.

 

Business Requirement :

 

Restrict leave request below ½ day for SL & CL (Minimum ½ day can be avail) And 1 day for PL (Minimum 1 day can be avail). It will be applicable for all employees and this change will be effective from 01.08.2014


For this We have done below settings in rounding rule and counting rule,

And we have positive Time Management and back ground job scheduled as PT60 run on daily basis from 1st Nov 2013 (Go-live date +TM)

Since 1st Nov 2013, Many employees applied CL/SL hourly based like one & two hours

Now, After TM Executed (PT60) since 1st Nov 2013, system changed these hourly deduction as minimum half day deduction for previous period also.

But Business requirement is only effective from after 1st August 2014 only.


And there is no Delimit option in Rounding & Rounding rule to provide closing period until 31th July 2014 and start with new rule from 1st Aug 2014

So kindly suggest how to delimit rounding & rounding rule.


Please screens for reference,


Rounding Rule:V_T559R

1.png

Counting rule   T556C

2.png.jpg

 

3.png.jpg


Infotype 2011

4.png


Time Evaluation Message ( PT60)

5.png

Thanks in advance

Prabu


Viewing all articles
Browse latest Browse all 7926

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>