Dear SAP Experts,
Sorry for the long post please read thru and let me know your thoughts.
Reg Installation of Add-on SAP LOCHRSAE, below components are
prerequisites in ERP 6.0 EHP7 system as per note 1550973.
SAP_HR 604 604 SAPKE60435
EA-HR 607
The add-on LOCHRSAE 605 modifies the component SAP_HR. If you have
already imported more Support Packages for this component into your SAP
system than are specified in this note in the section "Required
Components and Support Packages", you must check whether Conflict
Resolution Transports (CRTs) of the add-on LOCHRSAE 605 are available.
For more information, see Note 1551074 . The CRTs are available on the
SAP Service Marketplace. If a CRT you require is not yet available, you
cannot perform the installation at present. For more information about
CRTs, see Note 53902.
But after installation of ERP 6.0 EHP7 SAP HR package level is in SP 75
and EA HR is in 607 26, so for these SAP HR package level how should we
proceed with applying LOCHRSAE Add-on.
Or let me know if we can proceed with applying addon with the below SP
level as in the note 1551074 and there wont be any issues.
SAPK-60539INLOCHRSAE LOCHRSAE 605 SP38
SAP_HR 604 SP75
EA-HR 605 SP52
or EA-HR 606 SP37
or EA-HR 607 SP26
SAP Notes Referred :
1550973 - Installation of LOCHRSAE 605 on ERP6.0 EHP5-6-7 HR renewal 1.01551073 - Release strategy for the ABAP add-on LOCHRSAE
1551074 - Support Package Note for Add-on LOCHRSAE 605
Kindly suggest on the below ASAP as we are waiting to install the add-
on.
Thanks