Hi All,
It is general scenario in middle ast to calculate PY for 30 days, we edited PCR XPP1 a sbeloe wmentioned and it will work for individual days
Eg: upto still 27 day sin feb, or 30 days months, but when employe etake leave for whole feb 2 days extra sal is getting processded, how we can stop this and bring to 30 days exact calculation.
*
/801 Partial period factor 1
RTE=TKDIVP Set
RTE-TKAU** Subtraction
RTE*KGENAU Multiplication
RTE/ 30 (KZDIVI Division (30 days –T511k))
ADDWT * OT Output table
refering below tread also :
http://scn.sap.com/thread/1588990