Dear Team,
Due to election, client has declared the holiday (suppose 6th May). In sap we have created the floating public holiday with holiday class 1. This floating public holiday assign with holiday calendar.
In the last Generate Work Schedules Manually (Change work schedule) - given the details, generate
& save the work schedule.
Client is using positive time management & employees are applying leave, OT, clock in/ out etc through ESS.
While applying the work on holiday they unable to apply, got the following error:-
“The selected day is not a holiday”
Kindly suggest!
Thank you in advance
Regards,
Rakesh