Hi Gurus,
Right now i am doing positive time management, Here i'm getting doubt like
1. I've copied TM04 into ZM04
2. Maintained time management status in IT 0007 -- 1 ( time evaluation of actual times )
3. In generation of quota T559L table Calendar year & No prorata base
4. In Quota type selection V_556A_B maintained Increase
First my doubt is can i use TM04 for Positive time management?
Because I've copied TM04 in ZM04 for positive time evaluation & above mentioned points I've run time evaluation through PT60, here i did't get any error but quota is't generated kindly let me know what is the problem?
Image may be NSFW.
Clik here to view.
Image may be NSFW.
Clik here to view.
Ur'sImage may be NSFW.
Clik here to view.
Mohan